For a straightforward 5,000 square foot fit-out with a complete set of drawings, plan on 14 to 22 weeks from signed contract to move-in. Roughly four to eight of those weeks happen before anyone swings a hammer — permit review, submittals and equipment ordering — which is the part most schedules get wrong.
Construction itself on that size job usually runs 8 to 12 weeks. When a project blows its date, the cause is almost never framing or drywall.
Four things run in parallel, and each can become the critical path:
Any one of those can quietly add a month. Running them sequentially instead of simultaneously is the single most common scheduling mistake.
On a typical Albany office fit-out, the order rarely changes:
Inspections gate the whole thing. Work cannot be concealed until it has been seen, so an inspection that slips three days can slip the project a week once trades have to be resequenced.
In order of how often it happens:
Occupancy requires a certificate of occupancy or a temporary CO from the city, and that requires passing final inspections — building, electrical, and fire. Furniture delivery should be scheduled after the CO is in hand, not before. Buildings full of furniture are harder to inspect and harder to fix.
Build two weeks between substantial completion and your first day of business. That window absorbs punch list work, final cleaning, cabling termination and the things nobody thought of, without your staff working around a contractor.
Ask for a schedule with named milestone dates, updated weekly, showing what is on the critical path right now. "We're on track" is not a status. A one-page updated schedule with dates that move when reality moves is the difference between knowing you have a problem in week four and discovering it in week twelve.
Agree at the start how long the owner has to respond to submittals and requests for information. Five business days is a reasonable standard, and writing it down makes both sides accountable to the same clock.
Work backward from the date you must be operating, and add the pre-construction phase honestly — permit review, submittals and procurement, not just the build. If the arithmetic does not reach, the choices are a phased move-in, a reduced first-phase scope, or a later date. Discovering that in week one is inexpensive; discovering it in week ten is not.
Clifton Development Group runs office fit-outs and tenant improvement projects in Albany NY and across the Capital Region, including Troy, Schenectady, Saratoga Springs, Colonie, Clifton Park and Latham.
Further reading: CDG
Clifton Construction - General Contractor Albany NY
1024 Broadway
Albany, NY 12204
518-205-3673
Commercial general contracting, office fit-outs and building renovations across Albany, Troy, Schenectady, Saratoga Springs, Colonie, Clifton Park and Latham.